"Watch them Flourish" Update

Click the collage above to see more pictures.

Click the collage above to see more pictures.

The dining hall and kitchen are starting to look like a dining hall and kitchen. The sinks, dishwasher, stoves, ovens and the rest of the kitchen equipment will be installed and hooked up this week. The walk in cooler and freezer are up and running. (We have ice cream!) The spiral duct work in the dining hall is going up this week as work continues on the tongue and groove. The bathrooms have been tiled and the toilets are being set in place. The septic tank prep work has begun. The trailshack has also really come together this month thanks to volunteers from Gethsemane Lutheran Church, and Mackenzie (the cabin moved and rebuilt in the Hillside Village) is almost complete thanks to volunteers from Faith United Lutheran Church in Iron. We hope you can join us at the Dining Hall dedication in a few weeks.

-Gregg Velander
Project Manager